How to track RFIs on a construction bid

An RFI log is one numbered list of every question you asked and every answer you got, with who it went to, when it is due and what it changes. Kept well, it stops the same question being asked twice and keeps answers from missing the estimate.

The short version

While you price a job, questions pile up: two documents give different counts, a spec section refers to a drawing that is not there, a requirement is unclear. Each one becomes a request for information (RFI) to the owner or consultant. Without a log, they live in email threads, and an answer that arrives three days later is easy to miss or never act on.

What goes in an RFI log

FieldWhy it is there
NumberA short reference (RFI-001) you can use in emails, meetings and the estimate
Subject and questionOne question per RFI, worded so it can be answered without a call
Document and pageThe sheet, section or page the question is about, so the reader finds it in seconds
TradeSo the right estimator and the right subcontractors see the answer
Sent to, and whenWho was asked and the date, because "I asked last week" is not a record
Reply dueThe date you need the answer by, so late replies are visible
Answer, who gave it, and where it is writtenThe answer in the sender's words, plus a pointer to the email or addendum
What it affectsScope, quantities, price, schedule or nothing, so you know what to update

How to write an RFI that gets a useful answer

The fire damper example is illustrative. Counts that differ between documents are one of the most common reasons to raise an RFI.

Check the bid instructions first

Many formal bids set rules for questions: a named contact, a deadline for questions and a way answers are shared. Answers are often issued to every bidder, sometimes as an addendum. Read the instructions before you send anything, and do not rely on a verbal answer for something that changes your price. If your question would reveal how you plan to price, think about whether you want that shared with competitors.

Statuses that keep the log honest

  1. 1

    Draft

    Written but not yet sent. This is the only status where deleting is acceptable.

  2. 2

    Sent

    Out the door, with a date and a reply-by date. If the reply-by date passes, it is overdue.

  3. 3

    Answered

    You have a reply and you have recorded who gave it and where it is written.

  4. 4

    Closed

    You have acted on the answer: updated the quantity, the price or the package. Closing means the work is done, not only that a reply came.

Two more states matter: an RFI you decide not to ask can be withdrawn, and an answer that turns out to be wrong or incomplete can be asked again.

What to do with an answer

How ScopeMark runs the log

Owners and project managers raise and answer RFIs. Office admins can read the log. Field staff do not see it.

Common mistakes

Questions people ask

What is an RFI in construction bidding?

An RFI, or request for information, is a written question sent to the owner or consultant about something unclear, missing or conflicting in the bid documents. The answer is recorded so everyone prices the same reading.

How do I write a good RFI?

Ask one question, name the document and page, say what you found, offer an assumption they can confirm and ask for a reply by a specific date earlier than your bid closing.

Should I wait for an answer before I price?

It depends on the closing time and the bid instructions. If the date is close, estimators often price the most likely reading and state the assumption in the bid where the instructions allow it. Check the instructions for what qualifications are accepted.

Does ScopeMark send RFIs to the owner?

No. ScopeMark numbers and tracks the RFI. You copy the question into your own email, then press "I sent it" to record who it went to, when, and the reply-by date.

Does recording an answer update my estimate?

No. A person updates quantities or prices and then closes the RFI. Answers that affect scope, quantities or price are flagged on the estimate so they are checked before a quote is exported.

Can the whole RFI log be exported?

Yes. The log downloads as an Excel file with overdue RFIs marked.

Does ScopeMark hold or move our money?

No. ScopeMark does not process payments between companies and subcontractors. The buyer pays directly, outside ScopeMark, and records the payment. ScopeMark's only revenue is its subscription.

Related