How to review a construction tender or RFP before you price it

Read a tender in a fixed order: the bid instructions, whether you are eligible, what could cost you, the scope, the schedule and what is unclear. Then make the bid or no-bid call and write down why, before you spend time pricing.

The short version

A tender package can run to hundreds of pages, and most of what decides your bid is on a handful of them. The way to review one is to read in a fixed order and stop at each step to answer one question, so you decide whether to bid before you spend time pricing.

Review it in this order

  1. 1

    Read the bid instructions first

    Closing date, time and place, how bids are submitted, who you may ask questions and by when, what must be in the bid, whether a site visit is mandatory, and what security or bonds are required. Missing a submission rule can disqualify a bid, so this comes before anything else.

  2. 2

    Decide whether you are eligible

    Check the requirements against your own position: bonding capacity, insurance limits, required experience, certifications and safety record. If you cannot meet a mandatory requirement, you have your answer before reading further.

  3. 3

    Scan the contract for what could cost you

    Look at the contract form and general and supplementary conditions for liquidated damages, holdback, payment terms, change procedures, warranty, insurance and termination. Many Canadian tenders use standard-form contracts such as the CCDC documents, with amendments. Flag anything unusual for your lawyer instead of interpreting it yourself.

  4. 4

    Understand the scope for your trades

    List the divisions and trades involved, read the specification sections for the work you will price, and compare them with the drawings. Note quantities, products, exclusions and work done by others.

  5. 5

    Check the schedule

    Note the start, milestones, phasing, access hours and completion date. A schedule you cannot meet is a reason not to bid.

  6. 6

    Write down what is unclear

    Conflicts between documents, missing sheets and vague requirements become questions. See how to track RFIs on a bid, and read every addendum as it arrives.

  7. 7

    Make the bid or no-bid call and write the reason

    Bid, pass, or bid with conditions. Keep the reason, so next time you can see why you pursued or passed on a type of job.

  8. 8

    Split it into packages

    For the trades you will sub out, write a clear scope of work for each, so the bids you get back can be leveled like for like.

A one-page checklist

ItemWhere to lookThe question
Closing and submissionBid instructionsWhen, where and how must it arrive?
QuestionsBid instructionsWho may we ask, and what is the last day?
Bid security and bondsBid instructions, general conditionsWhat is required, and can we provide it?
InsuranceGeneral or supplementary conditionsWhat limits are required?
Liquidated damages and holdbackContract conditionsWhat are the amounts and the release terms?
Site visitBid instructionsIs it mandatory, and when?
Subcontractor rulesBid instructionsMust trades be listed, and by when?
Scope and quantitiesSpecifications and drawingsWhat is included, and do the documents agree?
ScheduleBid instructions, conditionsCan we meet the dates and phasing?
AddendaIssued during the bid periodHave we read and acknowledged them all?

Common traps

How ScopeMark helps

The AI writes a first pass for a person to check. It does not give legal advice, it does not price, and ScopeMark submits nothing for you. See how ScopeMark handles an RFP, from upload to a won project.

Questions people ask

What is the difference between a tender and an RFP?

The words are often used interchangeably in Canadian construction. A tender often means a price submitted against fully defined documents, and an RFP often means a proposal that includes approach as well as price. Your documents will say which process applies.

What should I read first in a tender package?

The bid instructions. They set the closing time, the submission method, the question deadline, the required forms and any mandatory site visit, and missing one can disqualify a bid.

How do I decide whether to bid?

Check eligibility (bonding, insurance, experience), the contract risks, the scope against your capacity and the schedule. Record the decision and the reason either way.

Can AI review a tender for me?

ScopeMark's AI drafts a first pass with page citations for a person to check. It shows what it cannot verify as unknown, does not price, does not give legal advice and submits nothing.

Should a lawyer read the contract?

For anything unusual in the contract conditions, yes. ScopeMark flags contract and legal items for counsel instead of interpreting them.

Does ScopeMark hold or move our money?

No. ScopeMark does not process payments between companies and subcontractors. The buyer pays directly, outside ScopeMark, and records the payment. ScopeMark's only revenue is its subscription.